4 August 2014

24X7 Electricity Supply

Electricity is a concurrent subject and the supply and distribution of electricity in a State falls under the purview of respective State Government/State Power Utility. The Central Government supplements the efforts taken by the State Governments in providing 24x7 electricity supply to all consumers. This was stated by Sh. Piyush Goyal, Minister of state for Power, Coal & New and Renewable Energy (Independent Charge) in a written reply to a question in the Rajya Sabha today.

The Minister further stated that to meet the entire power needs of the country an integrated approach is followed for the development of the power system. For the 12th Five Year Plan, Generation capacity addition of 88,537 MW of Conventional Sources and 30,000 MW of Renewable Energy Sources have been planned to meet the projected demand for power as per 18th Electric Power Survey (EPS). Commensurate transmission network of 1,07,440 circuit km and transformation capacity of 2,82,750 MVA have also been planned for evacuation of power. Central Government supplements the distribution network through Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY) and Restructured Accelerated Power Development & Reforms Programme (R-APDRP). Central Government is also assisting the States in formulating schemes to supply 24x7 power to their consumers, the Minister added. 


PIB

Power Generation Targets

The Ministry of New and Renewable Energy has set a target of capacity addition of 29,800 MW from various renewable energy sources during 12th Plan period. The target comprises of 15,000 MW from wind, 10,000 MW from solar, 2,100 MW from small hydro and 2,700 MW from bio-power. This was stated by Sh. Piyush Goyal, Minister of state for Power, Coal & New and Renewable Energy (Independent Charge) in a written reply to a question in the Rajya Sabha today.

The Minister further stated that the Ministry of New and Renewable Energy has prepared a Strategic Plan for New and Renewable Energy Sector in the year 2011 which has indicated a cumulative installed capacity of renewable power to about 72,000 MW by 2022. 


PIB

Solar Powered Lighting Solutions

The Government implements schemes for cost effective solar power lighting solutions for rural population in electrified/unelectrified areas and villages in the country that may have an impact on kerosene subsidy bill. Lighting up about 47 percent of the country population will depend on the fund availability in the respective programme. This was stated by Sh. Piyush Goyal, Minister of state for Power, Coal & New and Renewable Energy (Independent Charge) in a written reply to a question in the Rajya Sabha today.

Details of programme implemented by MNRE and Ministry of Power (MoP) are as under

I. Ministry of New and Renewable Energy (MNRE) is implementing Remote Village Electrification (RVE) Programme for providing financial support for lighting/basic energy using renewable energy sources including solar energy in those remote unelectrified census villages and unelectrified hamlets of electrified census villages where grid extension is not found feasible by the State Governments and hence are not covered under the Rajiv Gandhi Gramin Vidyutikaran Yojana (RGGVY). The programme is implemented in States by State Nodal Agencies.

II. Ministry of New and Renewable Energy (MNRE) is also implementing Off-grid and decentralized solar applications scheme of Jawaharlal Nehru National Solar Mission for installation of solar PV systems and power plants in various parts of the country including power deficit areas/unelectrified areas.

III. Ministry of Power is implementing Decentralised Distributed Generation (DDG) scheme under Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY) for electrification of villages where grid connectivity is either not feasible or not cost effective. In XII Plan, DDG has also been extended to the grid connected area where supply of electricity is less than 6 hours a day. Decentralized Distributed Generation (DDG) can be from conventional or renewable sources including solar energy.

Both under the DDG scheme of Ministry of Power and RVE programme of MNRE, the Government provides subsidy of 90% of the project cost. Under the DDG scheme, the balance 10% can be arranged by the Implementing Agency at their own or arranged from any financial institutions/Rural Electrification Corporation (REC), whereas for RVE projects the balance 10% cost of projects for remote village electrification is financed through contribution from the state governments and beneficiaries, etc. However, it is necessary that at least half of the balance cost is met from state government’s funding.

The RVE projects are taken up only in remote unelectrified census villages and unelectrified hamlets of electrified census villages where grid extension is not found feasible by the State Governments and hence are not covered under the RGGVY.

The norms followed for solar photovoltaic (SPV) based DDG projects are that the average household load should not be more than 100 watt, population of the villages/hamlet should be more than 100 and cost norms of MNRE benchmark to be followed.

Under the Off-grid and decentralized solar applications scheme of Jawaharlal Nehru National Solar Mission, the Ministry of New and Renewable Energy provides 30% capital subsidy for installation of solar PV systems and power plants in various parts of the country including power deficit areas/unelectrified areas. (90% capital subsidy for Government organizations of special category States).
--PIB

Power Generation from Renewable Energy Sources

The Ministry of New and Renewable Energy has set a target of capacity addition of 29,800 MW from various renewable energy sources during 12th Plan period. The target comprises of 15,000 MW from wind, 10,000 MW from solar, 2,100 MW from small hydro and 2,700 MW from bio-power. This was stated by Sh. Piyush Goyal, Minister of state for Power, Coal & New and Renewable Energy (Independent Charge) in a written reply to a question in the Rajya Sabha today.

            The Minister further stated that the details of power generated from the renewable energy sources in the public sector undertakings under the control of Government as well as in the private sector during 2012-13 and 2013-14 are 47.61 billion units and 53.22 billion units respectively.

            An amount of Rs 19,113 crore has been provided for promotion and generation of renewable energy during the Twelfth Five Year Plan period. The funds allocated for 2012-13, 2013-14 and 2014-15 are as below:-
Year
Budget Estimate (in Rs. crore)
Physical Target(In Megawatt)
2012-13
1385.00
4125
2013-14
1521.00
4325
2014-15
2519.00
3770




The Minister further stated that Budget allocation for the years 2015-16 and 2016-17 will be allocated after approval of Annual Plans by the Government and Physical Targets will be fixed accordingly
-PIB