Renewable Energy Certificates
1. Central Electricity Regulatory
Commission (CERC) has introduced Renewable Energy Certificate (REC) concept,
which is a market based instrument, to fulfill the obligation of Distribution
Companies in respect of renewable power.
Both the Energy Exchanges in the country have started trading the RECs
to the DISCOMs and other obligatory entities from March 2011.
2. Basically, Renewable Energy project
developer has got following two options –
a) To Sell the power at a
preferential tariff;
b) To sell the power on a
Pooled Cost basis to DISCOMs and sell the RE Certificates separately through
Exchanges.
3. Conceptually, this instrument was borrowed
from CERs. Though Electricity Act, 2003
does not define renewable part of the electricity, but MNRE has defined certain
categories of power as renewable power for which a separate tariff is
determined by the State Regulator, such as (a) Wind power (b) Biomass power (c)
Hydel power with less than 25 MW and (d) Solar power.
4. Few of the project developers have been
encouraged to sell renewable power to the market and also sell renewable energy
certificates through Exchanges. All the
Regulators have now defined that the power taken by DISCOMs should have minimum
percentage of renewable power which is varying from state to state. For instance, Maharashtra and Gujarat have
got 9%( including solar of 0.5%) of the
renewable power obligation, whereas few states, like Jharkhand and Bihar have
got less than 2%. Mumbai does not have renewable power as such for the
following reasons:
(a) The wind power have got
noise pollution and birds would migrate;
(b) Biomass power requires a
good tract of land which is not available in Mumbai;
(c) Solar power has got
chemical disadvantages
5. Thus, all three Distribution Companies
of Mumbai are buying renewable power of some quantum from state based renewable
power project developers at a tariff determined by the regulator and remaining quantum
they are buying through renewable energy certificates and the cost of buying
such certificates are passed on to consumers.
For environmental point of view such steps are welcome but the problem
is that Mumbai has become the first place in the country which is buying huge
quantities of RECs. One RE of 1000 units
cost Rs.1500/-, which is equivalent to Rs.1.50 per unit and in a preferential
rate, buying 9% of RE would increase the cost of the power procurement
substantially, say by 2 to 3% . Similarly for solar the cost of these
certificates are Rs9300 and for 0.5% the cost increase by around 1%
7. Secondly, even buying renewable power
at a preferential tariff except for biomass, other power like wind comes into
rainy season and solar comes into day time.
One more anomaly is that on the basis of legal opinion, CERC asked Open
Access consumers to buy REC without framing the law and only regulation has
been passed. The second is that electricity
component in the renewable energy constitutes only 60% and 40% is from other sectors like
transportation etc. There is no burden
on transportation, aviation, mining and other sectors which are equally
responsible for emissions . Further for
offgrid power there is no control of Regulators . For instance country uses
around 10,000 Mw of diesel which also emit carbon but does not entail RECertificates
.
8. The country does not have a Renewable
Energy law or Renewable Energy Regulator.
Electricity component is taken care by Electricity Regulator Commission,
as Reliance Infra has in its clarification said that the tariff is determined
by regulator and it is high time that regulator be asked to be consumer
friendly and stall the RPO for the Mumbai till other states also follow the
suit. Maharashtra can make
representation to MERC and forum of Regulators to stall the Renewable Power
Obligation till maturity takes place and thus will save burden on the consumers
of Mumbai.
************
12वीं पास के लिए JNNSM में वैकेंसी, जल्द करें एप्ला3ई
ReplyDeleteReadmore Todaynews18.com https://goo.gl/XbO3rc